Road improvements are moving forward in Texarkana, Arkansas, with three streets now under contract.
Road improvements are moving forward in Texarkana, Arkansas, with three streets now under contract.
The city has signed contracts with Francis Excavating for work on East 48th Street, Oats Street and East 24th Street.
Mobilization is expected the week of August 17, with completion targeted for December 14.
Contracts have also been approved for four additional streets, including Sanderson Lane, Garland Avenue, Senator Street and Washington Street.